Sungai Lebam Water Treatment Plant Distribution Upgrading, Kota Tinggi

A new balancing reservoir and treated water pipeline are being constructed to support the Sungai Lebam Water Treatment Plant’s distribution system in Pengerang, Kota Tinggi.

Project Details
Owner: Pengurusan Aset Air Berhad (PAAB)
Consultant: DNP Consult Sdn Bhd
Main Contractor: Ikatan Gemajaya Sdn Bhd
Start Date: 9 June 2025
Completion Date: 18 December 2026
Contract Value: RM13.6 million

Project Description
Body: This package involves construction of a new 9.09 million litre balancing reservoir at Sungai Lebam, Pengerang, along with treated water pipeline installation and associated infrastructure, mechanical, and electrical works to ensure the water supply system operates at full capacity.

Scope Of Work

  • Site clearance and demolition of existing structures
  • Earthworks including excavation, filling, and compaction
  • Construction of a 9.09 million litre balancing reservoir
  • Supply and installation of MSCL pipes, 600mm to 700mm diameter
  • Installation of an 800mm diameter main transmission pipe connecting the new reservoir to the existing 800mm MSCL pipeline, approximately 0.45km
  • Road paving works
  • Drainage system works
  • Water reticulation works
  • Area lighting, electrical systems, and related services
  • Construction of fencing, entrance gate, and project signage

Status Note
As of the time of writing, this project remains under construction.